North west transmission line
Electrical Utilities / Products
OWNER
B.C. Hydro
CUSTOMER
Burns McDonnell
OUR SCOPE
Design assist, Detail and Fabricate Various Guyed Tower Foundations
QUANTITY
600 tons
TIMEFRAME
June 2012- Sept. 2013
CHALLENGES
The low temperature steel grade requirements for this contract made material procurement difficult and design alterations were necessary to allow use of material sections available in the specified grade.
-Another challenging requirement was for a “Paint over Galvanized” coating system in order to achieve a 70 yr. lifespan.